BRICKBHARAT
infrastructure · cities · Navi Mumbai

Atal Setu–Mumbai-Pune Expressway Link Road 67% Complete; 7.35-Km Elevated Road Bypasses Panvel

By BrickBharat Editorial Desk
Published: 13 November 2026 at 6:46 pm IST

MMRDA says the six-lane, 7.35-km elevated road linking Atal Setu to the Mumbai-Pune Expressway through Chirle and Palaspe has reached 67% physical progress, with deck slabs on about half the Chirle spans done.

A long sea bridge across Mumbai harbour
Atal Setu, the Mumbai Trans Harbour Link, which the new elevated road will connect to the Mumbai-Pune Expressway. Photo: Amitbalani / Wikimedia Commons (CC0).

The elevated road linking Atal Setu to the Mumbai-Pune Expressway has reached 67% physical completion, the Mumbai Metropolitan Region Development Authority (MMRDA) said in a progress update reported on 13 November 2026.

The 7.35-km, six-lane road is being built through Chirle and Palaspe in Navi Mumbai. It is designed to let traffic coming off Atal Setu, the Sewri–Nhava Sheva sea bridge, reach the expressway without passing through the congested Panvel junction.

Atal Setu–Mumbai-Pune Expressway link road: work done so far

The Chirle section is the most advanced. All 113 piles and 42 open foundations are complete, and 153 of 155 columns have been erected, or about 98%. Girder casting and fabrication are largely done.

Deck slabs, which form the road surface, are complete on 117 of 240 spans, or 49%. Reinforced earth walls, which hold up the approach ramps, are 90% done, and the railway overbridge on this stretch is 85% complete.

The Palaspe section trails behind. Fifteen of 21 pile-group foundations are finished, column casting stands at 38%, and girder casting is complete. Its reinforced earth wall panels are also 90% done, while its railway overbridge is under construction.

In April 2026, MMRDA had said the project was on course for completion by February 2027, according to the Free Press Journal. The latest update did not restate a deadline or a project cost.

Why the connector matters

The road is built at a third level above existing roads and bridges. MMRDA says it will cut travel time from South Mumbai to Pune by about 60 to 90 minutes, depending on traffic, once open.

It will also improve links between the expressway and the Mumbai-Goa highway, and towards Navi Mumbai International Airport and Jawaharlal Nehru Port. The authority says it will ease passenger and freight movement on NH-48 and NH-348.

Chief Minister Devendra Fadnavis said cutting travel time and improving freight efficiency were central to the state's infrastructure push. Deputy Chief Minister and MMRDA chairman Eknath Shinde said the benefits of such projects must reach commuters, while Metropolitan Commissioner Dr Sanjay Mukherjee called 67% progress an important stage for the project.

What it means for you

For commuters and businesses, a signal-free run from Atal Setu to the expressway would make the bridge far more useful for Pune and Goa-bound trips, and for trucks heading to the port.

For homebuyers, the connector strengthens the case for areas around Ulwe, Panvel, Kharghar and the new airport, which already gained from Atal Setu. Better road access often supports demand, but buyers should weigh on-ground timelines, since construction schedules on large projects frequently slip.

Investors tracking the Navi Mumbai and Raigad belt should watch for the opening date. Price moves in such corridors tend to follow actual commissioning more reliably than announcements.

Sources

Frequently asked questions

What is the Atal Setu–Mumbai-Pune Expressway link road?

It is a 7.35-km, six-lane elevated road being built by MMRDA through Chirle and Palaspe in Navi Mumbai to connect Atal Setu directly to the Mumbai-Pune Expressway, bypassing Panvel junction.

How much of the Atal Setu link road is complete?

MMRDA has reported 67% physical progress. In the Chirle section, 153 of 155 columns and 117 of 240 deck-slab spans are done.

When will the Atal Setu–Expressway connector open?

MMRDA had targeted completion by February 2027 as of April 2026; the latest progress update did not restate a deadline.

More Indian real estate news